Bayou Des Cannes Water System engaged the services of A&A to make improvements to their water system. The improvements included the addition of 2 manganese greensand pressure filters, 1 zeolite softener with associated piping, valves, electrical, generator, site piping and sitework to the existing water treatment plant, a 40' x 60' metal building, two 800 GPM water wells, 1275 new radio frequency water meters, a meter reading system which utilizes radio frequency interface units coupled to enhanced absolute encoder water meters, and hand held meter reading equipment.
Engineering and related services for the design and construction of demolition of existing hydraulic baffles, repairing leaking nitrification zone materials, pond level control gate controller and flow meter and ultra violet light disinfection system and installation of hydraulic baffles, pond level control gate controller and flow meter, ultraviolet light disinfection system, modular insulated pond cover, Lemna polishing reactor, and associated piping, valves, electrical, etc.
Demolition of an existing clarifier mechanism, installation of 32 foot diameter replacement clarifier mechanism, and construction of synthetic filter plate sludge drying beds with polymer injection system and mechanical bar screen including associated piping, valves, electrical, etc.
WATER TREATMENT PLANT IMPROVEMENTS
Improvements to the existing water treatment plant including the addition of two (2) ten (10) ft. manganese greens and pressure filters, two (2) six (6) ft. zeolite softeners, piping valves, and associated appurtenances; and a ten (10) ft. building addition including electrical and site work
WATER WELLS
Two (2) 800 GPM Water Wells
CONSTRUCTION OF OFFICE BUILDING
Construction of 1800 S.F. brick veneer office building including sitework, foundation, plumbing, electrical, mechanical, paving, etc.
DISTRIBUTION LINE IMPROVEMENTS
Consisted of four phases totaling 261 miles of distribution lines in Bell City, Hayes, Lowry, Welsh, Roanoke, Lacassine and Lake Arthur